Skip to main content
ByJuly 23, 2026~7 min read

Israel's Grid Freeze Re-Ranks Data-Center Projects by Connection Certainty

The 140-day pause turns a signed grid commitment into a project-selection asset. Shoham and Har Tuv disclose 60 and 96 MVA, while Hadera already carries major land capital and Enlight remains at the MOU stage.

The 140-day review freeze does not automatically reward every developer that already bought land or announced a data-center strategy. It makes a signed grid commitment and reserved network capacity decisive inputs into project probability. Mega Or offers the clearest example: it says the power required for existing hosting agreements is already supported by connection approvals, while expressly withholding that conclusion from future projects and agreements. Nofar Energy at Shoham and the Har Tuv project promoted by Doral Energy and Ampa disclose 60 and 96 MVA, but still need to connect that power to customers, permits and financing. At Hadera, Mega Or has already paid NIS 1 billion for land and estimates total acquisition costs at roughly NIS 1.1 billion without matching disclosure of approved capacity for the future project. Enlight Energy has yet to disclose a detailed agreement, a selected site or defined power capacity. The regulatory order therefore reorders the pipeline by the quality of each connection right and by the capital committed before that right was proven.

The Regulator Freezes the Queue Before Setting New Rules

Noga has approved more than 1,500 MW of data-center connections, while accumulated requests reached roughly 27,000 MW. That gap explains why the Electricity Authority paused reviews for facilities of 8 MVA or more for 140 days rather than merely extending response times. The system figures and policy directions under discussion were detailed in July's regulatory coverage.

The intervention was not unexpected. February's inter-ministerial report had already called for rules preventing non-viable projects from blocking grid capacity, faster treatment in preferred regions and better integration of renewable generation and storage. The freeze converts those policy ideas into an immediate business constraint.

Mega Or currently interprets the order as allowing projects with signed commitments and properly reserved capacity to continue technical coordination and connect on their original terms. That is the company's preliminary assessment, not a new project-by-project confirmation from the regulator. The distinction also matters within Mega Or. Its annual project tables separated 314 MW IT under construction from 280 MW IT on land designated for future development. The July update addresses power required by hosting agreements already signed. It does not confer blanket protection on the full future pipeline.

Our previous analysis of the electricity bottleneck identified the grid connection as the sector's critical asset. The new event adds a binding pause that lets the state reassess which commitments correspond to projects capable of being built.

A Grid Commitment Outranks Land and an MOU

ProjectWhat has been demonstratedWhat remains missingCurrent read
Mega Or's existing hosting agreementsConnection approvals for the power required by signed agreements, based on the company's preliminary reviewFinal confirmation of scope and delivery against scheduleHighest-certainty layer, limited to existing agreements
Nofar Energy's Shoham projectAgreement to acquire rights in about 32 dunams, approval for 60 MVA and planned capacity of 45 MW ITCompletion conditions, final financing and a binding customer agreementMost mature disclosure among new projects without a signed customer
Har Tuv by Doral Energy and AmpaA 96 MVA system-operator commitment, phased connection and exclusive rights to develop about 74 MW ITLease, end user, permits and confirmed economicsMeaningful grid right, with earlier-stage commercial closure
Mega Or's Hadera siteAbout 180 dunams acquired, NIS 1 billion paid and zoning that permits data centersDisclosed approved capacity, project size, construction cost and financingMajor capital committed ahead of power proof
Enlight Energy's MOUProposed 50/50 ventures covering data centers, storage, solar and power supplySite, capacity, connection, customer, investment and detailed agreementStrategic option, not yet a project

Shoham ranks ahead of Har Tuv on overall readiness even though Har Tuv discloses the larger grid commitment. Nofar Energy signed a NIS 361 million land-rights transaction and disclosed its payment structure, partnership and connection status. Har Tuv has an exclusive development agreement, but its lease may be signed only later, within four years, and the arrangement can be terminated if permits, an end user or economic viability do not materialize. Its 96 MVA therefore does not yet equal contracted cash flow.

Land Ties Up Capital While Grid Decisions Wait

The difference is not merely legal. It determines who finances the waiting period. At Hadera, Mega Or paid the full purchase price through a shareholder loan to Mega DC from the parent's own resources, carrying market-rate interest. The property currently produces negligible rent, while project scale, construction cost and financing remain undefined. A regulatory delay does not necessarily create an immediate accounting loss, but it lengthens the period in which NIS 1 billion of capital is not advancing toward project income.

Nofar Energy's staged payment structure reduces part of the immediate cash risk. The first NIS 36 million of the NIS 361 million consideration is placed in escrow and released only after agreed conditions are met. The minority partner, however, can require Nofar Energy to acquire its partnership interest within 12 months of possession for roughly NIS 36 million plus a 10% annual return and the outstanding balance of its shareholder loans. Final project financing and total investment have not been closed. The 60 MVA approval improves the starting position without removing the capital burden.

Har Tuv does not require the joint venture to acquire the land immediately. Its structure defers the lease and permits an exit before possession if the business conditions fail. Doral Energy and Ampa therefore carry less sunk project capital at this stage, but they also lack a lease and customer that would turn the grid commitment into cash flow. Enlight Energy has no binding project economics yet, so the demonstrated cost is mainly development time and foregone optionality rather than disclosed project investment.

On-Site Power and Storage Still Need a Grid Path

The emerging policy gives weight to location, local generation and storage. The inter-ministerial document presents them as tools for reducing pressure on the power system and increasing the number of projects that can connect. It does not treat them as an automatic substitute for a connection commitment.

That distinction is particularly important for Enlight Energy. Its MOU contemplates storage, solar generation and electricity supply at its partner's properties, with a detailed agreement targeted within 60 days and a possible 30-day extension. The document identifies no site, capacity, backup design or connection approval. Energy capabilities may improve readiness after a project is defined, but the current disclosure does not place the venture alongside Shoham or Har Tuv.

The current hierarchy puts Mega Or's contracted layer first. Shoham follows, combining land and 60 MVA approval but still lacking a final customer and financing. Har Tuv has a larger grid commitment but must complete its lease, customer and permit stack. Hadera bears the largest disclosed land-capital burden relative to missing connection disclosure, while Enlight Energy's MOU remains an early option.

Final criteria can alter that order, particularly if existing commitments are reassessed for readiness, financial capacity or location. Even after publication, the companies should not be compared on one equity multiple. They span real estate and renewable energy, own different project shares and disclose different layers of investment. A binding customer, attributable capex, debt structure, economic ownership and confirmed connection right are still required to translate this operating hierarchy into project value and shareholder contribution.

Disclosure: Deep TASE analyses are general informational, research, and commentary content only. They do not constitute investment advice, investment marketing, a recommendation, or an offer to buy, sell, or hold any security, and are not tailored to any reader's personal circumstances.

The author, site owner, or related parties may hold, buy, sell, or otherwise trade securities or financial instruments related to the companies discussed, before or after publication, without prior notice and without any obligation to update the analysis. Publication of an analysis should not be read as a statement that any position does or does not exist.

The analysis may contain errors, omissions, or information that changes after publication. Readers should review official filings and primary sources before making decisions.

Found an issue in this analysis?Editorial corrections and sharp feedback help keep the coverage honest.
Report a correction