Hachshara Hitachdashut: Is HaAliya HaShniya the 2026 Engine or the Next Bottleneck
In the March 2026 presentation, HaAliya HaShniya in Haifa looks like one of Hachshara Hitachdashut's main 2026 anchors: 715 housing units, 539 for marketing, and projected gross profit of ILS 135 million for the company's share. But the building permit is still conditional, Bayit Vagag currently sits more as a financing layer than as realized value, and the move into execution still depends on the bank, the contractor, and completion of the remaining conditions.
The main article argued that Hachshara Hitachdashut has already started the move into execution, but the shareholder test still runs through cash, partners, and the ability to turn pipeline into actual execution. HaAliya HaShniya in Haifa now concentrates all three variables in one project. In the March 2026 presentation it looks like one of the company's biggest 2026 engines. In the partnership note and in the permit report it still looks like a project sitting between a conditional permit, a financing bridge, and an execution phase that has not yet been locked in.
That is exactly the point that can be missed on a fast read. If the reader looks only at slide 15, the project already looks almost ready: 715 housing units, 539 units for marketing, 96% signings, a 50% company share, projected gross profit of ILS 135 million, and an expected move into construction readiness during 2026. Once note 18 and the December 2025 permit report are read alongside it, a different picture appears. Under that headline still sit a full building permit that has not yet been obtained, bank financing that has not yet been closed, a contractor agreement that has not yet been signed, and a partner loan whose repayment terms have already become relevant.
So the right question is not whether HaAliya HaShniya is important. Clearly it is. The real question is what stage it is actually in. Right now it is less a running engine and more a very large 2026 option, with meaningful upside but also with several failure points that the company itself explicitly flags.
Why HaAliya HaShniya Immediately Stands Out
At the scale level, it is hard to find another Hachshara Hitachdashut project that concentrates volume, relative maturity, and profit potential in the same way. The permit report describes a project with 715 new housing units and 16 commercial units, replacing 176 existing apartments in the complex. Out of that, 539 housing units and 6 commercial units are meant to be marketed by the developers. The presentation already places the project inside the group of projects expected to be ripe for marketing and execution in 2026, with a 96% signing rate.
The profit numbers shown in the presentation also explain why the market may read HaAliya HaShniya as a 2026 engine. Slide 15 attributes projected gross profit of ILS 135 million to the company's share of the project, with a projected gross margin of 17%. That is a large enough number to matter for a full year in a company of Hachshara Hitachdashut's size.
But this is where note 7(d) matters. On the 2025 year-end balance sheet, inventory and land for construction attributed to HaAliya HaShniya amount to only ILS 13.9 million, up from ILS 9.5 million at the end of 2024. That number is not small because the project is small. It is small because the project has not yet made the jump into the stage where execution, bank support, and construction start to flow through the balance sheet on a very different scale. In other words, the presentation is already speaking the language of future gross profit, while the balance sheet is still speaking the language of pre-execution.
That is the core gap. HaAliya HaShniya is large enough to support a 2026 headline, but as of the end of 2025 it still does not look like a project that has completed its regulatory and funding de-risking.
The Problem Is That The Permit Has Not Yet Turned Into Execution
In the immediate report dated December 24, 2025, the company did not say that it had received a full building permit. It said that the local planning committee in Haifa had decided to approve the application for a full building permit subject to conditions. In that same report, the company states explicitly that the full permit is expected during the third quarter of 2026, and that construction works are expected to start only after that point.
That wording matters a great deal because it makes 2026 later-loaded than the presentation headline suggests. If the full permit is expected only in Q3 2026, and construction is supposed to begin only after that, then even in a positive scenario the project moves into full execution only in the later part of the year. That is not a problem if everything moves smoothly. It is a problem if the project is being read as if it is already a clean 2026 backstop.
The forward-looking caution in that same report explains why. The company itself says that the path from here to project execution still depends, among other things, on completing the conditions specified in the committee decision, obtaining the required approvals, completing individual agreements with all existing rights holders, signing a financing agreement with a financial institution, and signing an agreement with the executing contractor. In other words, between "permit approved subject to conditions" and "construction starts", there is still a full chain, not one final stop.
| Layer | What already exists | What is still missing | Why it matters |
|---|---|---|---|
| Planning and permit | Committee decision approving a full permit subject to conditions was received in December 2025 | Full permit is only expected in Q3 2026 | Without a full permit, the company itself does not present construction start |
| Rights and signings | The presentation shows 96% signings as of December 31, 2025 | The permit report still lists completion of individual agreements with all rights holders as one of the remaining conditions | A small gap in signings can become a large timing delay |
| Funding | There is an existing partner, a partner loan, and a mechanism for additional equity | A financing agreement with a financial institution is still required | Without a bank, the project does not move from a financing bridge to execution |
| Execution | There is a demolition permit and a decision on a full permit subject to conditions | A contractor agreement and the final permit are still needed | Even a large project does not begin on the strength of a presentation slide alone |
This is why HaAliya HaShniya is not yet a clean 2026 engine. It is a project that can become one, but for now it is also one of the places where a delay of several months can push the whole story from a 2026 execution window into a much tighter timeline.
Until The Full Permit Arrives, Bayit Vagag Looks More Like Funding Than Realized Value
Note 18(v) is the most important part of this continuation. It makes clear that the question is not only when the permit will be obtained, but also how the project is being held until that happens. In May 2023 the company signed a cooperation agreement with Bayit Vagag regarding HaAliya HaShniya, and in July 2023, after the condition precedent was met, it assigned 49% of the rights and obligations in the project to Bayit Vagag. Even so, project expenses, revenue, and profit are split 50%-50% between the parties.
That partnership comes with an explicit financing layer. Bayit Vagag extended a loan of ILS 30 million to the company. For 24 months the loan carried no interest and was not indexed. But if by that point no building permit had been obtained for the project, the loan would carry annual interest at prime plus 1% until the permit was obtained or the loan was repaid. In addition, after 24 months Bayit Vagag has the right to demand repayment, and if that happens before a building permit is obtained, that becomes a terminating condition that cancels the agreement. As of the financial statement date, Bayit Vagag informed the company that it had no intention of demanding the balance despite the condition not having been met, and if it does so the company has the option to defer repayment for one year.
This is not a footnote. It means that at the end of 2025, even after the December committee decision, the partnership is still operating around the flexibility of a financing partner rather than around a project that has safely crossed into bank-supported execution. The fact that the company felt it had to state that Bayit Vagag does not intend to demand the balance "despite the condition not being met" shows that HaAliya HaShniya was still sitting on the line between a funded option and an executed project.
There is a second layer here as well. Subject to the loan not being accelerated, and at the time of equity injection as agreed with the financing bank, Bayit Vagag is expected to provide additional excess equity of ILS 15 million for the company's share, against security over the company's share in the project surplus. That means even the next layer of partner capital has not yet reached the stage where it is execution capital. It is still conditional on the bank entering and on the existing loan not blowing up first.
That chart is not meant to add the numbers together. It is meant to show that they sit in four different layers of the same project. ILS 13.9 million is what already sits on the balance sheet. ILS 30 million is the financing bridge already in place. ILS 15 million is additional capital that is only supposed to arrive later, when the bank enters. ILS 135 million is the projected gross profit for the company's share shown in the presentation. Until the first three layers close, the fourth remains a future thesis rather than accessible value.
And this is where the sharpest line in the note appears. Because a building permit had not yet been obtained for the project, the company had not recognized income from derecognition of inventory, and all amounts received from Bayit Vagag are presented as liabilities. At the same time, the company recognizes a financing component at a rate of 9.75% on those amounts, added to the liability, with matching financing expense. In plain terms, as of the end of 2025 Bayit Vagag still looks in the financial statements less like realized project value and more like a financing layer waiting for the permit event that allows the project to move into its next phase.
What Must Happen For The Project To Become An Engine Rather Than A Bottleneck
HaAliya HaShniya can become one of the company's true 2026 anchors only if four checkpoints happen almost in sequence. The first is a full building permit, not only a permit subject to conditions. The second is closing bank financing. The third is signing the contractor agreement. The fourth is moving the Bayit Vagag relationship from a liability-with-financing-component structure into a situation where equity, bank support, and execution are actually operating.
If that happens, the presentation is probably not overstating the story. A project with 715 units, 539 units for marketing, 96% signings, and projected gross profit of ILS 135 million for the company's share can certainly become a meaningful engine. But if one of the intermediate steps slips, the same project can very quickly become the next bottleneck. Precisely because it is large, it cannot get stuck quietly.
That is why it is more accurate to read HaAliya HaShniya as a second-half 2026 project rather than as a project that already solves 2026. Even in the positive case, construction is supposed to begin only after the full permit arrives. So its contribution to the coming year should first be measured through the company's ability to remove the blockers, and only after that through execution itself.
Bottom Line
HaAliya HaShniya in Haifa is probably one of Hachshara Hitachdashut's most important projects on the way into 2026. But as of the end of 2025 and the March 2026 presentation, it is still not an engine that is already running. It is a very large project sitting in the middle of a transition. On one side there is a committee decision, a high signing rate, an existing partner, and large profit potential. On the other side, the full permit is still not in hand, the bank facility and contractor agreement are still not closed, and in the financial statements Bayit Vagag's money still looks like a liability with a financing component rather than value that has already been unlocked.
So the answer to the headline question is still open. If the full permit, the bank financing, and the contractor agreement close on the 2026 timetable the company is presenting, HaAliya HaShniya can become a real engine for the coming years. If one of those links is delayed, this is exactly the project that will remind investors how quickly the next flagship project can turn into the next bottleneck.
Disclosure: Deep TASE analyses are general informational, research, and commentary content only. They do not constitute investment advice, investment marketing, a recommendation, or an offer to buy, sell, or hold any security, and are not tailored to any reader's personal circumstances.
The author, site owner, or related parties may hold, buy, sell, or otherwise trade securities or financial instruments related to the companies discussed, before or after publication, without prior notice and without any obligation to update the analysis. Publication of an analysis should not be read as a statement that any position does or does not exist.
The analysis may contain errors, omissions, or information that changes after publication. Readers should review official filings and primary sources before making decisions.